1.活動房雨天施工時,宜搭設臨時防護棚,雨水不得飄落在熾熱的焊縫上.如焊接部位比較潮濕,必須用干布擦凈并在焊接前用氧炔焰烤干,保持接縫干燥,沒有殘留水分。
1. During the construction of activity room in rainy days, temporary protective shed should be set up, and the rain should not fall on the hot welding seam. If the welding part is wet, it must be cleaned with dry cloth and dried with oxyacetylene flame before welding, so as to keep the joints dry without residual moisture.
2.活動房吊裝時,構件上如有積水,安裝前應干凈,但不得損涂層,高強螺栓接頭安裝時,構件摩擦面應干凈,不能有水珠,更不能雨淋和接觸泥土及油污等臟物。
2. During the hoisting of the mobile house, if there is water on the component, it should be cleaned before installation, but the coating should not be damaged. When the high-strength bolt joint is installed, the friction surface of the component should be clean, without water droplets, rain, soil, oil and other dirt.
3.雨天天氣構件不能進行涂刷工作。
3. The component cannot be painted in rainy days.
4.雨天及五級以上大風不能進行屋面保溫的施工。
4. Roof insulation construction can not be carried out in rainy days and strong wind above level 5.
5.雨天由于空氣比較潮濕,焊條儲存應防潮并進行烘烤,同一焊條重復烘烤次數不宜超過兩次,并由管理人員及時做好烤記錄。
5. In rainy days, because the air is humid, the welding rod should be stored in moisture-proof and baked. The same welding rod should not be baked more than twice, and the management personnel should make baking records in time.
6.如遇上大風天氣,柱、主梁、支撐等大構件應立即進行校正,位置校正正確后立即進行固定,以防止發(fā)生單側失穩(wěn).當天安裝的構件,應形成空間穩(wěn)定體系。
6. In case of gale weather, the column, main beam, support and other large components shall be corrected immediately. After the correct position correction, they shall be permanently fixed immediately to prevent unilateral instability. The components installed on that day shall form a space stable system.